Project rendering of 120 Fifth Avenue as viewed from Fifth Avenue and Park Place space space space space space space space
Project Information
120 Fifth Avenue is a mixed-use development site in Park Slope, Brooklyn. Once completed, the 180-unit development will include:
- 45 affordable apartments
- A 25,000‐square‐foot community-oriented supermarket
- Approx. 42,000 square feet of additional retail/commercial space, including a CVS pharmacy, Wells Fargo bank branch and neighborhood retail
- A 130-space below-grade parking garage
- A publicly accessible pedestrian plaza connecting Butler Street with Fifth Avenue
Construction Hours
- Monday-Friday, 7:00am-6:00pm.
- Weekend work will be scheduled as needed, typically on Saturdays from 9:00am until 6:00pm.
- After-hours or Sunday work may be scheduled for public safety reasons or for the continuity of essential construction tasks (e.g., cement pours).
Construction Time Frame
The project’s construction team is committed to conducting work on the site in a manner that is responsible and respectful of the community while working to complete this project as expeditiously as possible and deliver the new supermarket and affordable housing units starting late 2024/early 2025. We greatly appreciate the patience of our neighbors during construction.
Completed Work on Site
- Site demolition, excavation and pile driving
- South Building topped out; exterior envelope enclosure for South Building complete
- Foundation work for North Building
- Delivery and assembly of a construction crane
- Limited tree trimming on Butler Street
- Removal of two street trees on 5th Avenue
Project rendering of publicly-accessible pedestrian plaza connecting Butler Street with Fifth Avenue (looking towards Fourth Avenue)
Upcoming Work on Site
- North Building structural work continues
- Delivery and installation of steel plinth beams for North Building
- Delivery of prefabricated metal stud walls for North Building
- Decking and concrete installation at North Building
- Interior work on South Building, including mechanical/electrical/plumbing work, sheetrock installation and window installation
- Hydrant Relocation on 5th Avenue
- Installation of Sidewalk Vault on 5th Avenue for utility connections
Construction Effects
In January, February, and March, you can expect the following:
- Truck deliveries within hours of operation. Our team has instructed truck drivers to park only where permitted; not to park in bus stops or crosswalks; not to block deliveries to local businesses or residential driveways; and to follow all applicable NYC regulations regarding idling. Our team will endeavor to minimize the impact of truck traffic around the site.
- Temporary sidewalk sheds to establish pedestrian paths and promote safety.
- Street parking is available on the west side of Gregory Place. The east side of Gregory Place (adjacent to site) is a “No Parking” zone.
- Construction vehicles will access the site via vehicular gates on Fifth Avenue and Gregory Place. Flagmen will be present to help ensure pedestrian safety as vehicles enter and exit the site.
- Seismic monitors on and around the site will report and track vibrations from construction activity in real time and ensure that all activity is within legally allowed limits.
If you have questions regarding this work, please call the 120 Fifth Avenue construction hotline at (347) 773-1174 or send an email to [email protected].