120 Fifth Avenue, Brooklyn
Construction Update
October/November/December 2025
Project rendering of 120 Fifth Avenue as viewed from Fifth Avenue and Park Place space space space space space space space
Project Information
120 Fifth Avenue is a mixed-use development site in Park Slope, Brooklyn. Once completed, the 180-unit development will include:
- 45 affordable apartments
- A 25,000-square-foot community-oriented supermarket, operated by Lidl
- Approx. 42,000 square feet of additional retail/commercial space, including a CVS pharmacy, Wells Fargo bank branch and neighborhood retail
- A 139-space parking garage
- A publicly accessible pedestrian plaza connecting Butler Street with Fifth Avenue
Construction Hours
- Monday-Friday, 7:00am-6:00pm.
- Weekend work will be scheduled as needed, typically on Saturdays from 9:00am until 6:00pm.
- After-hours or Sunday work may be scheduled for public safety reasons or for the continuity of essential construction tasks (e.g., cement pours).
Construction Time Frame
The project’s construction team is committed to conducting work on the site in a manner that is responsible and respectful of the community while working to complete this project as expeditiously as possible and deliver the new supermarket and affordable housing units starting in 2025. We greatly appreciate the patience of our neighbors during construction.
Upcoming Work on Site
- Finishing interior and façade work on both building
- Finishing all electrical infrastructure work
- Removal of modified pedestrian paths in front of North and South Buildings
- Street tree plantings on 5th Avenue and Baltic Street
- Work continues on new retail spaces
Project rendering of publicly-accessible pedestrian plaza connecting Butler Street with Fifth Avenue (looking towards Fourth Avenue)
Completed Work on Site
- Site demolition, excavation and pile driving
- North and South Buildings substantially complete
- Installation of loading dock on Baltic Street
- Removal of construction crane and hoist from site
- Limited tree trimming on Butler Street
- Removal of two street trees on 5th Avenue
- Relocation of fire hydrant on 5th Avenue
- Installation of sidewalk vaults on 5th Avenue for utility connections
- All construction sheds removed
- Sewer infrastructure work completed
- Electrification of both buildings
- All pedestrian paths restored
- Parking garage open
- Publicly-accessible Paseo pedestrian plaza open.
Construction Effects
In October, November, and December, you can expect the following:
- Truck deliveries within hours of operation. Our team has instructed truck drivers to park only where permitted; not to park in bus stops or crosswalks; not to block deliveries to local businesses or residential driveways; and to follow all applicable NYC regulations regarding idling. Our team will endeavor to minimize the impact of truck traffic.
If you have questions regarding this work, please call the 120 Fifth Avenue construction hotline at (347) 773-1174 or send an email to info@120fifthavenuebk.com.
Sign up to receive periodic construction updates at 120fifthavenuebk.com